SHUSWAP NORTH OKANAGAN RAIL TRAIL CONSTRUCTION MAKING GOOD PROGRESS WITH MILD WINTER WEATHER
January 23, 2026 FOR IMMEDIATE RELEASE Enderby, BC — Construction on the Shuswap North Okanagan Rail Trail is making strong...
April 14, 2026

April 14, 2026
FOR IMMEDIATE RELEASE
Construction on the Splatsin te Secwépemc / Shuswap North Okanagan Rail Trail is still underway, and the majority of the 50 kilometre trail is not yet open to the public. While some short sections are available for walking and cycling, most of the corridor remains closed due to ongoing construction, safety concerns, and required environmental work.
Limited Sections Currently Open
At present, approximately 19.8 km are open, spread across three disconnected segments:
There is no through travel between these sections, and access south of Mara Lake and north of km 0.5 remains closed.
The largest portion of the rail trail - particularly between Mara Lake and Enderby (km 15–42.6) - is currently under construction and not open to public access. Work includes trail building, erosion repairs, agricultural crossings, road crossings, signage, and environmental mitigation. Archaeological and environmental assessments are ongoing, as required.
Additional delays at the northern end, related to Bruhn Bridge construction in Sicamous, mean that the full northern trailhead connection will not be complete until 2027, even after the main trail corridor is built.
Funding is in place to complete most of the trail by the end of 2026, but the final 6.5 km section still depends on additional funding approvals. Until construction is finished, trail users should expect closures, detours, and changing access conditions, and should check for updates before visiting.
Trail users are reminded to stay on the trail and that dogs must always remain on leash. This requirement is an important part of the agricultural management plan to protect adjacent farming operations. Failure to comply may result in dogs being prohibited from the trail.
A Public Information Bulletin with access details, maps, and construction updates is available at
www.shuswapnorthokanaganrailtrail.ca
Media Contact:
Ken Barnes
Communications Specialist, Splatsin
Cell: (250) 801-8256; ken.barnes@splatsin.ca

January 23, 2026 FOR IMMEDIATE RELEASE Enderby, BC — Construction on the Shuswap North Okanagan Rail Trail is making strong...

News Release: January 24, 2025 Annual Shuswap Trail Alliance fundraiser continues online for 2025 The Shuswap,...

NEWS RELEASE, For Immediate Release December 20, 2024 ENDERBY, BC — The Rail Trail partners—Splatsin te...

News Release, September 5, 2024 Construction will continue throughout the fall on the rail trail between Sicamous and Armstrong. The rail trail...
Fostering a healthy, engaged community in the Shuswap Region – economic/environmental/social – through well designed, maintained, and promoted trails connecting people, culture, and landscape